Neuse River Resource Recovery Facility Bioenergy Recovery Program (NRRRF BERP) (Construction Manager At-Risk)

Raleigh, NC

Crowder was selected as the Construction Manager At-Risk for the construction, start-up, and commissioning of advanced biosolids treatment processes and ancillary facilities at the Neuse River Resource Recovery Facility (NRRRF), an advanced wastewater treatment facility with liquid treatment capacity undergoing expansion from 60 MGD to 75 MGD. Biosolids are currently processed through aerobic digestion to produce Class B liquid or through lime stabilization to produce Class A cake. Raw solids are also sent for off-site composting by a third party or landfilled. The project includes the transition to anaerobic digestion with thermal hydrolysis pretreatment to produce all Class A biosolids while moving toward energy neutrality. The project is currently in the construction phase.